paintingcontractorguides.com

Updated September 2026 · For Virginia painters taking on a pre-1978 exterior repaint

Repainting a 1962 house under the EPA lead rule

What does the lead rule change on a repaint of a 1962 house with peeling paint?

The estimate visit for a 1962 ranch in Roanoke

A 1962 house is covered before you climb a ladder. You give the owner the EPA pamphlet and collect a signed receipt before work starts.

The owner asks for a repaint, and the siding is peeling. Ask the build year, write it down, and treat the house as covered unless a test says otherwise. EPA says paid work that disturbs paint in housing built before 1978 requires certification.

60 daysThe rule requires firms to give owners the Renovate Right pamphlet no more than 60 days before work and to get a signed acknowledgment or proof of mailing. — 40 CFR 745.84, Cornell LII, retrieved 2026-09-29

Why scraping the peeling paint crosses the line

Outside, the small-job exclusion stops at 20 square feet. One weathered gable end can be larger than that by itself.

Once you pass 20 square feet, the whole job is a renovation under the rule. It does not matter that the rest of the house needs only a light coat. The exclusion is also lost if you use a prohibited method, however small the area.

20 sq ftThe minor repair exclusion covers 20 square feet or less of painted surface outside, when no prohibited practices are used and no window is replaced. — 40 CFR 745.83, Cornell LII, retrieved 2026-09-29

Setting up before the first scraper touches wood

Post signs that define the work area and keep them up until cleanup ends. Lay ground cover that extends at least 10 feet from the work.

The certified renovator has to be there for this. Then choose your methods. Torching the paint is banned. Power sanding or grinding needs a HEPA vacuum attachment. A heat gun must stay below 1,100 degrees Fahrenheit.

1,100 degrees FExterior work requires ground covering extending 10 feet or more from the renovation, and open-flame burning and heat guns above 1,100 degrees are prohibited. — 40 CFR 745.85, Cornell LII, retrieved 2026-09-29

Cleanup, verification and the last invoice

Collect the chips, roll up the sheeting, and clean with HEPA vacuums and damp cloths. Your renovator then checks the work and verifies it with cleaning verification cards.

Send the owner the compliance information when the final invoice goes out, or within 30 days of finishing, whichever comes first. Keep your records for 3 years.

Next, run the same steps against the job checklist before the next covered estimate.

30 daysFirms must give the owner compliance information when the final invoice is delivered or within 30 days of completion, whichever is earlier. — 40 CFR 745.86, Cornell LII, retrieved 2026-09-29

Questions

What if the peeling paint turns out to be a newer coat?

You need a test to show that. A certified renovator with an EPA-recognized test kit, a certified inspector or lab analysis can show that no lead-based paint is present. Without one of those, treat the house as covered.

Do I need to test every surface on the house?

The exclusion applies to components a qualified test shows are free of lead-based paint at 1.0 milligram per square centimeter. Untested components stay covered, so a partial test only clears what it tested.

Who pays for the extra containment and cleanup time?

The rule sets the practices, not the price. Build the extra setup, cleanup and verification time into the estimate before you quote, since the rule applies to the whole covered job.